For the first time in nearly a year, Rye Country Day School came before Rye’s city planning commission Tuesday to present significant campus upgrades on both sides of Boston Post Road. Based on the commission’s feedback, there’s still a long road ahead before the project gets the green light.
“There’s going to be a long process, and we need to go through it step by step. It’s hopefully a little quicker than The Osborn, but it may be similar to that,” said Chair Nick Everett, prefacing the RCDS presentation with a reference to the year-long review of the senior living community’s renovations.
The private school plans to build a new academic building and demolish the hockey rink on its current campus. On the 9-acre Thruway property, which the school purchased for $5.16 million in 2022, RCDS plans to build a new hockey rink, a multipurpose turf field, and a new field house with an indoor track. The construction of an underground tunnel would allow pedestrians safe travel to the new athletic complex on the other side of Boston Post Road.

The proposed RCDS plans would come in six phases, starting with six to eight months of “early site work,” which includes landscaping and the construction of the pedestrian tunnel. The academic building was slotted for Phase 3, before work on the various athletic facilities in Phases 4-6.
“Let me explain to you what I see as a major flaw and the reason that I think this is a failure,” Everett said. “I think you’ve got the academic building way too soon. You need to rethink your whole scenario so that the turf field is last.”
Drawing on his own experience, Everett called off-site parking with a shuttle service an “enforcement nightmare.” Rethinking the sequencing of construction, he said, would negate this because there would be more parking spots available on campus for the 100-plus workers needed to build the athletic buildings.
| Phase | Duration (months) | Workers needed |
| Early site work (landscaping, tunnel construction) | 6-8 | 30 |
| Underground parking | 10-12 | 50 |
| Academic building and temporary parking | 20-22 | 75 |
| Ice rink construction | 14-16 | 100 |
| Existing rink demolition | 4-6 | 30 |
| Field house and turf field completion | 18-20 | 125 |
Sixteen people packed into the City Hall conference room for the RCDS proposal, including several presenters: RCDS outside counsel Jonathan Kraut; Brian Morrissey, of Suffolk Construction; project architect Mark Thaler; environmental engineer Steven Lauria; traffic engineer John Canning; and landscape architect Michael Barnicle.
Renderings presented included sketches of the new proposed buildings viewed from the surrounding highways and roads. Dozens of architectural plans have been drawn up for construction of buildings and significant landscape alterations.
Perhaps chief among the committee’s frustrations was a mismatch between the school’s enthusiasm for its plans and, in contrast, the concerns it will raise for outside parties, both from an aesthetics perspective and how often the facilities will be available for use by the rest of the community.
“This will be an institutional-level piece of architecture that will be contextual with the architecture that’s on campus,” Kraut said. “It will be contextual with what Rye is expecting in terms of quality, and it will work hand in hand with the landscape.”
Commission member Laura Brett was not assuaged. She expressed sympathy for the project’s landscape architect and remarked that the current plan does not allow adequate space for substantial landscaping.
“One of the things that’s frustrated me about this project since it was introduced is that it’s hard not to contrast it with The Osborn,” she said of the project that received long-awaited commission approval in June. “You haven’t really thought about the buffers, you haven’t created a way to reduce the visual impact of this and really thought through making sure that there’s enough space to do that.”

The commission and school representatives agreed the city’s steep slope law presents challenges. Extremely steep slopes (gradients of 35 degrees or more) demand “rare and exigent” circumstances for construction to move forward via the planning commission. It’s a high legal standard, with just two options, according to Everett.
“It really ties our hands,” Everett said. “Either you need to go to the city council and get them to change the law, or you need to write a memorandum that we can hang our hat on and defend it. It puts us in an untenable position.”
Everett also promised the planning commission’s support if the school found itself before city council trying to change the law.
Another contingent for the sale of the 9-acre Thruway plot was that the school’s new amenities must be available for community use at least 29% of the time – but in what capacity? The commission asked for a more robust written outline of what this split would look like.
“Currently, Rye Country Day School, of its own volition, hosts a whole cadre of user groups,” Kraut said. “That is all happening presently on the western portion of the campus. The school has made clear, and it’s our intention, we’re not taking those uses that presently exist and saying, ‘We’re going to put them over here, and that’s our 29%.’ We understand that we’re trying to enhance and accommodate greater recreational opportunities for user groups.”
It’s not yet known when or how often RCDS will return to commission meetings. Remaining meetings for 2026 are set for Oct. 27, Nov. 17, and Dec. 15. The school was able to progress to this point because it was excluded from the six-month moratorium on city construction, which remains in effect until December. But as Everett and the commission noted Tuesday, there’s a lot of work to be done before the proposed plans can become a reality.